Quarterly report pursuant to Section 13 or 15(d)

Developments of Consolidated Outlet Centers (Tables)

v3.23.1
Developments of Consolidated Outlet Centers (Tables)
3 Months Ended
Mar. 31, 2023
Real Estate [Abstract]  
Schedule of Real Estate Properties
The table below sets forth our consolidated outlet centers under development as of March 31, 2023:
Project Approximate Square Feet
(in 000’s)
Estimated Total Net Cost
(millions)
Costs Incurred to Date
(in millions)
Projected Opening
New Development:
Nashville 290 
$142 - $150
$62.8 Fall 2023